Our Cherrystone reservoirs are being evaluated, as required, in accordance with Technical Release No. 210-60, Earth Dams and Reservoirs (USDA-NRCS, 2019). This directive requires our reservoirs to be evaluated as "High Hazard" dams, due to the potential impact a dam breach would cause to significant roads, railways, and populations living downstream in the event of a 1000 year rain event.  Both Cherrystone dams are structurally sound. However, the USDA-NRCS provided both direction and funding for the geotechnical study, and design of a rolled-concrete dam/spillway structure to satisfy the given definition of High Hazard dams. The pertinent documents are listed for your information.

Cherrystone Dam 1 Final Plan of Work

Cherrystone Dam 2 Final Plan of Work

Cherrystone Dam 2 Final Geotechnical Investigation Report

 

Cherrystone Rehab Project

Responsible Parties: NRCS, Pittsylvania County & Town of Chatham

May 2022-                         Inundation Study

December 2022-                Schnabel Engineering awarded work for geotechnical studies and design

September 2023-               Cherrystone Dam 2 Geotechnical Studies Completed & Submitted for review to NRCS

October 2023-                   Cherrystone Dam 1 Geotechnical Studies Completed & Submitted for review to NRCS

Future Timeline- TBD